The Army’s wider tactical communications programme received a red delivery confidence rating in February 2025, while the paused Morpheus project had already cost around £766 million.
The British Army’s Land Environment Tactical Communication and Information Systems programme was given a red delivery confidence assessment in February 2025, prompting a strategic reset after Project Morpheus had already been paused with expenditure of around £766 million, the UK Defence Journal understands.
The details are contained in a letter dated 17 August 2026 from Minister for Defence Readiness and Industry Luke Pollard to Conservative MP Mark Francois, deposited in the House of Commons in response to three parliamentary questions concerning the performance of the LETacCIS programme, the costs associated with Morpheus and the measures being taken to sustain the existing Bowman tactical communications system.
Pollard said the wider LETacCIS programme underwent an Infrastructure and Projects Authority-sponsored Gate 0 Review in February 2025, which resulted in a Delivery Confidence Assessment of RED. The subsequent review made several recommendations, including what the minister described as a strategic reset of the programme, after which the Army began work against those recommendations before a follow-up assessment was conducted in July 2025.
Pollard wrote: “I can confirm that in February 2025, the LETacCIS programme undertook a routine Infrastructure and Projects Authority sponsored Gate 0 Review which delivered a Delivery Confidence Assessment rating of RED. The subsequent report made several recommendations which included a strategic reset of the programme.”
He continued: “The Army immediately took action against the recommendations, and progress was later assessed in a follow up review in July 2025. Having demonstrated significant progress against all recommendations, the programme was reassessed as AMBER.”
The letter also provides a clearer figure for spending on Project Morpheus, which was intended to replace and modernise elements of the Army’s Bowman tactical communications architecture. Pollard confirmed that Morpheus was paused following the conclusion of the Evolve to Open Transition Partner contract in December 2023, by which point approximately £766 million had been spent on the project.
He said: “The MORPHEUS project paused on conclusion of the MORPHEUS Evolve to Open Transition Partner contract in December 2023. At that point, spend to date on the project was c.£766 million.” Pollard added that commercial sensitivities prevented the Ministry of Defence from providing a more detailed breakdown of expenditure across development, industry partnerships, external advice and sustainment activities.
The minister stressed that Morpheus formed only one part of the wider LETacCIS programme and said the Army had continued pursuing its underlying objectives since the end of the Evolve to Open contract. Rather than proceeding through the original Morpheus structure, tactical communications updates are now being delivered through what Pollard described as an iterative and incremental approach under the revised Land Domain C4 sub-portfolio.
The document also addresses the position of Bowman, which remains in operational use while the Army develops its replacement arrangements. Pollard said the Ministry of Defence had continued to meet operational requirements despite delays to Morpheus, with the Bowman Combat Infrastructure and Platform project being used to make incremental changes addressing known obsolescence and security issues.
Pollard wrote: “Despite the delays experienced by Project MORPHEUS, the Ministry of Defence has continued to meet all operational requirements. Through the BOWMAN ComBAT Infrastructure and Platform (BCIP) project, iterative and incremental updates continue to be undertaken to address known obsolescence and security requirements.”
He added: “These updates will ensure BOWMAN remains a capable and credible system until replaced. There are currently no plans to extend BOWMAN’s out of service date.”












Big surprise, another General Dynamics f**k up. At this point I really can’t think of a single project being delivered by a US Defence contractor that’s anywhere near being delivered on time and in budget.
tuned out at 700 millon
Is there ANYTHING that MOD procurement can do right?
Everything they touch seems to be doomed to failure
How about giving the suppliers penalties for not reaching certain benchmarks? Oops sorry the MOD also writes the contracts that appear to have more holes than a colander.
Every new government we hear changes will be made to improve procurement. It never does. It seems to get worse
Still never mind directorships for all senior officers and MOD bureaucrats in said defence companies
you see im saying im not that carazy
serious i laugh its stuff need made blitz cities
“The Army immediately took action against the recommendations”
For a non English native speaker the use of “against” in this context always makes my brain puzzled.
Why not?
“The Army immediately took action following the recommendations”
You are quite right, Alex. Your grasp of the English language would appear to be superior to that of a UK Minister of State! However, it may have been written for him by a lesser mortal.
Puts me in mind of one of the posters on this very blog who sometimes writes (as an example) “We should of bought British kit” instead of “we should have bought British kit”. Ah well…
certain care that it works and quality name alone is sad red be considerd marxist
well im just saying maine
manny mon knock these lumps out with a hammer
brutal place id laugh
Heading towards a billion for a communication system improvement that is anything but. That’s about 3 T31’s, maybe more.
Have they tried WhatsApp?
Not sure what goes on in procurement, but it’s cluster after cluster, with even bigger ticket prices! I was impressed by Bowman (eventually) and the Harris kit, so is this a real step change across the board or another UK specific requirement change? I’ve still got a bit of BATCO knocking about, deffo confuse just about anyone born after 2000!
Of course this is only half the story. GD were in a no lose situation and it was not in their interest to have MORPHEUS as a working EVO (Evolve to Open) system. Why would GD want to replace their proprietary Bowman system with an Open system? As the encumbant Bowman supplier GD knew they would get further contracts to update BCIP ; and so it proved, GD funded a further £100M for the BCIP 5.7 to keep the obsolete Bowman hobbling along. GD never delivered the deliverables due under the Morpheus contract (which was originally valued at £330M but somehow cost taxpayers £766M!) because they knew they didn’t have to.
SO GD delivered nothing and according to James Cartlidge fell short of what was required – SO why pay them £766M? Why is MoD not demanding their money back? Ajax all over again!
GD promise to deliver something, then fail to perform and get paid anyway! I guess it is not as bad as Ajax where the MOD have wasted approaching £7,000,000,000 of taxpayer money on an obsolete concept that doesn’t and can’t be used as it is unsafe. The really concerning thing is Army top brass regard Ajax as an opportunity!! UK Army plan to spend billions more on an obsolete fiery coffin for the cavalry – perhaps they should revert to horses like the Russians have?
In effect GD had the MoD by the balls, knew it and probably never intended to deliver an ‘Open’ system – why would they
Besides, Signals senior officers need a retirement plan.
👍indeed…..