The Ministry of Defence’s procurement organisation warned it was already operating unsustainably, with an 18% shortfall in the capacity it needs, and that planned workforce cuts would make this significantly worse, according to the National Audit Office.

The NAO found the MoD has only “limited assurance” that it can carry out everything the £298 billion plan envisages. Its report states: “During the DIP process, NADG made adjustments totalling £12.5 billion to its four-year cost forecasts so they reflected its overall assessment of what it and industry would be able to deliver. However shortly before the DIP process concluded, NADG warned that it was already operating unsustainably due to the imbalance between programme scope and delivery capacity. NADG identified that it had an 18% shortfall against the forecast capacity needed, and that it had to close this gap to 10% to manage the capacity risk. Planned reductions to its workforce would make this problem significantly worse. NADG warned that it would either need to spend more on contractors in the short term or stop work on several important ongoing programmes (in addition to those already paused or cancelled by the DIP).”

The NAO’s press summary states: “The MoD considers the DIP to be broadly affordable over the four years to 2029-30, but recognises some costs are likely to rise. However, it faces risks to delivering the DIP. Its procurement arm is already operating unsustainably, while workforce reductions and the deferral of spending beyond 2030 could increase pressure on both the MoD and industry at a time of growing demand.”

The National Armaments Director Group, which includes Defence Equipment and Support, also agreed late in the process to defer £1.4 billion of capital spending from 2026-27 and 2027-28. The NAO said the MoD did not have a definitive set of measures to achieve those savings at the time, although it told auditors its planning had since matured.

The NAO warned of a ‘bow wave’ of pressure after 2030, as the plan assumes about 20% of project costs will not be spent as planned. It said: “The longer-term DIP plans will require NADG to spend significantly more money after 2030, as new programmes get underway. NADG is aware that it will need to make sure its workforce is suitably sized and skilled before this spending increase; if NADG is not prepared, projects will start more slowly, and military capabilities would be likely to enter service later than planned.”

The MoD has a target to cut civil service-related costs by at least 10% by 2030. In September 2025, then minister Al Carns said: “Importantly, this is a productivity-driven ambition, not a headcount target,” the UK Defence Journal reported. The NAO found “emerging evidence that the civil service reduction targets were leading MSHQ to replace some civil servants with military personnel, even though civil servants are cheaper to employ.”

The NAO also identified areas with significant delivery challenges, including munitions, integrating uncrewed ships and aircraft with crewed platforms, which “will mean NADG and the industry need to work in a different way and require changes to regulatory regimes”, and research and development, where the MoD “is not currently ensuring new technologies are developed into usable capabilities quickly enough.”

This month, the procurement organisation has continued to award major contracts. The MoD selected HII for a £303 million Royal Navy contract for eight uncrewed mine hunting systems, with the contract due to begin on 25 November after the standstill period was extended, according to a contract award notice.

The MoD also said it intends to directly award Babcock a contract worth around £340 million for light aerobatic training aircraft and instructors from 2030, on the grounds that only one supplier can meet the requirement, according to a transparency notice published on 20 November.

Gareth Davies, head of the NAO, said: “The Ministry of Defence has taken important steps to improve its understanding of the cost of its investment plans. But much remains to be done to ensure the Defence Investment Plan can be delivered as intended.

“The department must now monitor the Plan closely, maintain accurate cost information and be transparent with Parliament about emerging pressures.”

George Allison
George Allison is the founder and editor of the UK Defence Journal. He holds a degree in Cyber Security from Glasgow Caledonian University and specialises in naval and cyber security topics. George has appeared on national radio and television to provide commentary on defence and security issues. Twitter: @geoallison