All of the Ministry of Defence’s red-rated major programmes can be recovered and none is being lined up for cancellation at this stage, National Armaments Director Rupert Pearce told the Defence Committee, though he admitted the position had worsened since he took up the post.

Labour MP Emma Lewell said fifteen major defence programmes across all three services had been assessed as red by the National Infrastructure and Service Transformation Authority, with completion largely in the 2030s or unknown, and asked whether they had stayed in trouble during Pearce’s time in post. Pearce replied: “It’s got slightly worse, actually.” Asked whether the programmes were recoverable, he said: “All of them. All of them are recoverable. Red is a statement not of inevitable failure, but that unless something is done, which means could involve a reset, it could involve more money, it could involve dealing with very specific issues.”

Asked whether any should be scrapped, Pearce said: “At this stage, we’re not looking to scrap any of these on the list.” He accepted that dates on the programmes would slip further, saying: “Yes, it will. If things if things slip if if it takes. I mean, generally, to fix these programs, it’s just going to take time and money to get to where we need to be.”

On the armoured cavalry programme, Pearce said Ajax “is a has been a deeply troubled program, and we’re on at least our second reset.” He added: “There are lots of reasons for that. It is a very complex program, and you know I don’t think it was set up for success looking back.” He said one of the frailties was that the system “kind of stopped when the vehicle was delivered out of the the factory”, and that training and the onboarding of operations had to be reinvented.

Pearce said the troubled programmes were an inheritance, telling MPs: “None of the things that are red were greenlit in the last year, so that’s why I talked about it as an inheritance.” He said 42% of the department’s large projects were delivered on time, to budget and to requirements, against a benchmark figure of half a percent in the Bent Flyvbjerg data set for large programmes, adding: “Now, one should take no pleasure from any of those numbers. It’s pretty shocking to me, actually.”

Lewell said: “I think it’s just frustrating for us as a committee because procurement and delays to programs have been a long-running theme for as long as I can remember.” Permanent Secretary Jeremy Pocklington told the committee the figure was “15, 16 of 44” programmes.

In March, Pearce said the share of programmes in difficulty was “just over 20% pushing 25% now – it’s too high”, adding that “most of those programmes are not over budget. They’re delayed”. In January, the Ministry of Defence formally withdrew initial operating capability for Ajax and moved responsibility for the programme away from the Army, after John Healey, then Defence Secretary, told the Defence Committee ministers had not had the full facts, as we reported. Healey said: “I am furious that vital information was withheld.”

NISTA’s annual report, published in July, rated 34 of 189 government major projects red at the end of March 2026, according to the government. NISTA chief executive Becky Wood said: “These assessments should not be seen as a definitive judgement on whether a project will ultimately succeed or fail.”

Last month, industry bodies told the Defence Committee the Defence Investment Plan was “not investable as it stands at the moment”, and ADS chief executive Kevin Craven warned that building a new production line from scratch takes two to four years.