Defence Equipment and Support intends to buy life rafts for the RAF’s E-7 Wedgetail from AEM Limited without competition, saying any delay would significantly set back the aircraft’s Airborne Mission System release to service, according to a transparency notice.

The UK5 transparency notice, published on 27 October, sets out an intended direct award worth about £220,000 and gives 6 November as the earliest date the contract can be signed. Justifying the urgency, it said: “There is an urgent need to procure and reconfigure the life rafts by November 2026. Any delay will result in a significant delay to the Airbourne Mission System release to service. Testing and acceptance of the life rafts has already been undertaken.”

The work covers nine life rafts for the E-7 platform at RAF Lossiemouth, the reconfiguration and recertification of three existing rafts, four rafts for training with a servicing cycle each quarter for 12 months, and an instruction manual. The contract is estimated to run to 28 February 2028.

The notice also cites intellectual property as grounds for the direct award, saying AEM “has exclusive rights within the United Kingdom, on behalf of the Original Equipment Manufacture to supply, maintain and service equipment.”

The first aircraft, WT001, arrived at Lossiemouth on 21 May and will complete test and evaluation at MOD Boscombe Down and Lossiemouth before formal transfer from Boeing UK to the RAF, after which 8 Squadron will operate it. The UK Defence Journal also reported that a second aircraft was due to begin test activities soon after arriving at Lossiemouth and a third was still being modified at STS Aviation in Birmingham.

George Allison
George Allison is the founder and editor of the UK Defence Journal. He holds a degree in Cyber Security from Glasgow Caledonian University and specialises in naval and cyber security topics. George has appeared on national radio and television to provide commentary on defence and security issues. Twitter: @geoallison

22 COMMENTS

  1. Not exactly going to lose sleep over this but the optics don’t look great here as presented, using ‘urgency’ and avoidance of ‘delay’ as the excuse for awarding this contract seems odd considering how long they have had to realise they would need life rafts for the aircraft and thus study the best process to acquire them over the long delayed project. It simply sounds, right or wrongly, like they all walked into meetings with the assumption that someone else was sorting out the process only for when it was finally raised there was dead silence in the room as everyone simply stared at those around them. All it lacks is a Peter Sellers figure in the prime role of a remake of I’m Alright Jack.

    • I suspect it’s more down to it being a very small contract probably with one obvious supplier in place but they have to use the terminology to bypass the procurement process.

    • It does give it a very unplanned feel as the need for hte life rafts would have been in the program for some time.

      I am guessing they were pushed to the right as there was no money and now there is a collision between no money and no planes. Now, The Minister has been asked what to do: some money have been found from the tea fund.

      I do get the feeling that his alter ego Jacques is working hard in the background……

      • I would concur with your comments, how the hell did it get to the point that the procurement , and an obviose one at that considering the phrase “Maritime Patrol” of life rafts for the aircraft became urgent! Some folks need a big kick up the arse for dropping the ball.
        I know the aircraft is multi function etc but it was bound to be transiting water at some stage, or being used over water! It is getting beyond stupid now. What’s next……forgot to order propellers for a ship i suppose.

    • They were exactly what the customer wanted at a reasonable price. Might even be the only one on the market which matches the spec. They have this process exactly for these circumstances. If we want cheaper, quicker procurement we should encourage use of this process.

  2. If memory serves, we used beaufort MS10 liferafts on the Nimrods. One installed in each wing housing and two inside the fuselage for fast access.
    Not sure whether they have a similar setup with these jets, but would have thought it would have been at the forefront of the design discussions.

  3. I’m sure there’s shed loads of life saving equipment on the beaches of Dover etc! Or in the intervening period just make sure you only patrol above the English Channel, as if you have to ditch you will be picked up in about 7 seconds, then get a new mobile phone, new clothes, a bit of time in a hotel, then a cash card and get sent off to recuperate in a small middle class English Village!!!