The Ministry of Defence has told its teams that work on some projects can only start once funding for the whole project is available, in a bid to end a culture of approving business cases on the basis that affordability would be resolved later, according to the National Audit Office.
The NAO’s report states: “The MoD intends to mitigate cost growth by strengthening its system for approving project proposals. Internal guidance on implementing the DIP, issued in July 2026, states that some investment decisions would be sequenced by priority and work could only be started when funding for the whole project was available. This was to address a culture within the MoD whereby it approved business cases with a view that affordability would be resolved later.”
Auditors said the guidance requires each of the MoD’s four areas to produce updated ten-year financial forecasts, identify projects that could be deprioritised if required, and ensure forecasts exclude undeliverable activity. The report states: “The MoD does not intend that this implementation process revisits DIP decisions, but that it translates those decisions into detailed programmes, budgets and delivery plans that areas can implement.”
It adds: “To support robust planning and governance, the guidance introduces clearer forecasting, costing and reporting requirements. Areas must distinguish between approved activity, pipeline activity and proposed changes to scope, explain variances from the DIP, comply with updated forecasting guidance, and reflect departmental priorities such as efficiency targets, workforce planning, digital expenditure transparency, and investment in novel technologies.”
The NAO noted that it had previously reported the MoD including part-funded programmes even though the overall Equipment Plan was unaffordable, and that the Defence Committee had criticised the department’s willingness to commit to spending beyond its future budget in expectation of an uplift. It also said: “In some previous years, the MoD has set additional efficiency targets shortly before finalising its spending plans in order to make them appear affordable – even if the efficiency assumptions were not realistic. It deliberately sought to avoid doing that during the DIP process.”
The Defence Investment Plan replaced the annual Equipment Plan, which the MoD published from 2013. The last Equipment Plan data, from December 2023, showed ten-year forecast spending on equipment to 2032-33 was £16.9 billion more than the budget, with an overall defence budget shortfall of £42.5 billion over the period, the NAO said.
At the time, the NAO found forecast costs of £305.5 billion against a £288.6 billion budget, the largest deficit since 2012, and nuclear and naval programmes drove most of the increase, the UK Defence Journal reported. Gareth Davies said then: “The MOD acknowledges that its Equipment Plan for 2023–2033 is unaffordable”.
In January 2021, the NAO found the 2020 to 2030 Equipment Plan unaffordable for the fourth successive year, according to UK Defence Journal reporting. Auditors warned then: “The MoD continues to make over-optimistic and inconsistent judgements when forecasting costs.”
In October, industry witnesses told the Defence Committee the Defence Investment Plan was not investable as it stands, the UK Defence Journal reported, in the same month the Chancellor set a 2030 target date for 3% of GDP. Streeting told the Committee he was “not comfortable” that more than £1 billion had been moved out of the housing budget during the process, according to the UK Defence Journal.
Gareth Davies, head of the NAO, said: “The Ministry of Defence has taken important steps to improve its understanding of the cost of its investment plans. But much remains to be done to ensure the Defence Investment Plan can be delivered as intended.
“The department must now monitor the Plan closely, maintain accurate cost information and be transparent with Parliament about emerging pressures.”