The Ministry of Defence’s Commercial X fast-track buying unit had delivered 850 contracts by March at an average of 31 days from requirement to contract, 47% faster than comparable procurements, according to an answer given in Parliament.

Conservative MP Stuart Anderson asked what assessment had been made of the effectiveness of procurement reform to date.

Luke Pollard, Minister for Defence Readiness and Industry, said: “We inherited a procurement system that was slow, expensive and unsuited to the threats we face as a nation. Reforming it was and remains a priority for this Government. The Ministry of Defence has made significant progress, including through the establishment of the National Armaments Director Group, streamlined commercial pathways and a more flexible, segmented approach to acquisition. Early results show the positive impact of our procurement initiatives like Commercial X, delivering 850 contracts by March 2026 at an average of 31 days to contract, 47% faster than comparable procurements. Further work continues to embed these reforms consistently across Defence to demonstrate sustained improvements in capability delivery, value for money and industrial productivity.”

Asked how many major programmes have adopted accelerated procurement pathways, Pollard said: “Accelerating Commercial Pathways (ACP) provides practical commercial tools, guidance and support to help teams deliver programmes faster and more effectively. The Programme empowers commercial professionals to make greater use of existing flexibilities within policy and procurement legislation, enabling better and more proportionate decision-making. The Programme helps to shift behaviors from compliance-led processes to outcome-focused delivery. Rather than relying on standard approaches regardless of circumstance, teams are encouraged to select and tailor commercial strategies that best support Programme objectives and delivery timelines. ACP has developed multiple pathways to address specific procurement challenges and delivery needs. These include Spiral, Urgent, Design to Cost, Digital and Technology, Low Complexity Procurement, SME, and SPARX pathways, each designed to support different operational and commercial circumstances.”

Commercial X was set up in 2022 to get new technology to the armed forces faster and make it easier for small firms to work with Defence. Its guidance page recorded 580 contracts and £74 million in savings as of December 2025, meaning a further 270 contracts were added in the following three months.

Neither answer gave a number of major programmes. Independent scrutiny has been more cautious about the wider system. The National Audit Office, reviewing the Defence Investment Plan this week, quoted the National Armaments Director Group as saying “NADG has identified that its own processes are rigid, limiting how much it is able to do concurrently,” the auditor found.

The Public Accounts Committee warned in June that delay to the Defence Investment Plan was “seriously undermining the Department’s efforts to modernise the Armed Forces and achieve value for money for the taxpayer,” the committee said, adding that it risked weakening the industrial base, with smaller firms hit hardest.

George Allison
George Allison is the founder and editor of the UK Defence Journal. He holds a degree in Cyber Security from Glasgow Caledonian University and specialises in naval and cyber security topics. George has appeared on national radio and television to provide commentary on defence and security issues. Twitter: @geoallison